Leuna Energy Park

Photovoltaics

Leuna Energy Park

Illustrative image

Solar power for the chemical park

South-west of Leuna, a solar park of approx. 52 MWp is being built on around 47 hectares of recultivated landfill. Its power flows through a long-term power purchase agreement (PPA) into the grid of InfraLeuna GmbH and supplies companies at the Leuna chemical park directly with renewable energy.

LIVOS Energies invests in the project. Solos GmbH is the partner for engineering, construction and operations.

Technology
  • approx. 52 MWp / 42 MWac, fixed-tilt, south-facing
  • expected yield approx. 57 GWh per year (P50)
  • earth anchors or screw foundations to protect the landfill cover
Timeline
  • Construction start: 25 October 2026
  • Grid connection: Q2 2027
Location
Leuna, Saalekreis district
Saxony-Anhalt, Germany
approx. 20 km south of Halle (Saale)
Capacity (approx.)
52 MWp
Yield p.a. (approx.)
57 GWh
Area (approx.)
47 ha
Grid connection
Q2 2027