Press release
Construction starts in Leuna
- Construction starts on 25 October 2026
- approx. 52 MWp of photovoltaics on a recultivated landfill
- Power for the Leuna chemical park via the InfraLeuna grid
- Grid connection in Q2 2027
Leuna, 17 October 2026 – LIVOS Energies will start construction of the Leuna Energy Park on 25 October 2026. On around 47 hectares of recultivated landfill south-west of Leuna, a solar park of approx. 52 MWp is being built, expected to generate around 57 GWh of electricity per year.
The power will be fed into the grid of InfraLeuna GmbH under a long-term supply contract and will supply companies at the Leuna chemical park directly. Solos GmbH is responsible for engineering, construction and operations. Grid connection is scheduled for Q2 2027.
With the start of construction, the first large industrial solar project of LIVOS Energies moves from planning to building.
About LIVOS Energies
LIVOS Energies invests in and operates energy infrastructure for industry: photovoltaics, battery storage and data centers. As part of LIVOS Gruppe, an investor and asset manager since 2005 with around EUR 1.5 billion in assets under management, LIVOS Energies stands for long-term capital and reliable delivery.
Contact
LIVOS Energies B.V.
John M. Keynesplein 1
1066 EP Amsterdam, Netherlands
info@livos-energies.com